Overview

TNG was commissioned to act as Client Advisor for a new student/residential construction that provided 50 self-contained studio apartments. This involved monitoring the detailed design of the modular build to ensure it met the Clients brief throughout the build.

The development consisted of a mixture of one, two and three bedroom units set around a central courtyard. The new build project also included a common social room and laundry, as well as an undercover car park and a bike store. Provision was also made for a commercial retail unit.

Pre-fabricated timber pods, which were manufactured in Latvia, were utilised by the Developer to support quick construction on site. This, therefore, enabled the new occupants to start settling in during the start of the new term.

TNG’s Services Included:

  • Monitoring the detailed design of the modular build to ensure it met the Clients brief, throughout the build.
  • Overseeing the installation of main plant equipment to ensure the installation quality.
  • Providing professional advice on the incoming services to site to ensure there was sufficient capacity for the mechanical and electrical services that would serve the new build.
Client
Brick Projects
Contractor
Nordic Construction
Architect
Studio Four Architects
Have a Question? Get in touch

We’re always available to chat and answer any questions you may have about our projects.

M&E
Client Advisor
RIBA
Work Stages 2-6